Library Notice -- Update on Improvement Measures and Construction Schedule for E2 Library Atrium Columns (2026-08-24)

Dear Students,

As the new semester begins, we fully understand students’ high expectations for a quiet and focused study environment. The library is currently undergoing maintenance work on the atrium columns. During the construction process, the inevitable noise, dust, and odor have impacted the study environment inside the library. We attach great importance to this issue and sincerely apologize for any inconvenience and disruption caused. To minimize the disturbance to our readers and enhance safety measures, we have coordinated further with the contractor to implement the following adjustments:

  1. Specific  Improvement Measures:

    §  Moving High-Noise  Work Outdoors: Material cutting and other high-noise, dusty work are now carried out outside the building to reduce disturbance.

    §  Strengthening Protection & Airflow: Safety barriers are reinforced and ventilation is enhanced to minimize dust and odor.

    §  Continuous On-Site Supervision: Staff will regularly inspect the site to enforce strict noise and dust control measures.

  2. Project Location and Affected Hours:

    §  Location: E2 Library atrium columns and surrounding areas

    §  Working Hours:  08:30 – 18:00 (No construction will take place after 18:00, ensuring your evening study remains unaffected)

    §  Estimated Completion: Originally set for Sept 18, the project would be slightly extended due to moving noisy work outdoors. Thank you for your understanding of this      adjustment made to minimize indoor disruption.

  3. Study Suggestions

       The library remains open as usual during the construction period. If you require a quieter environment for your studies, we recommend using the study areas by the windows in Zone A away from the atrium, or the private study rooms. If certain pathways are temporarily restricted due to the work, please follow the on-site signage.

This maintenance work is essential for ensuring building safety. While the project is necessary, the library has made every effort to coordinate with the contractor to implement multiple noise-reduction and dust-control measures to minimize the impact. We sincerely appreciate your understanding and cooperation, and we will continue to closely monitor the progress to restore a comfortable and quiet study environment as soon as possible.

If you have any suggestions or require assistance, please feel free to approach our staff at the service desk. We are always here to help.


UM Library